Loop Danışmanlık Grubu | Secondary Waste Water Treatment Plant and LPG Tank Project, Dubai, UNITED ARAB EMIRATES
17603
portfolio_page-template-default,single,single-portfolio_page,postid-17603,qode-quick-links-1.0,ajax_fade,page_not_loaded,,qode-theme-ver-11.0,qode-theme-bridge,wpb-js-composer js-comp-ver-5.1.1,vc_responsive
 

Secondary Waste Water Treatment Plant and LPG Tank Project, Dubai, UNITED ARAB EMIRATES

About This Project

“Secondary Waste Water Treatment Plant and LPG Tank” Project has been tendered by the Gas Authority in Dubai, and undertaken by Inco International Fz. Co. LLC as a turnkey industrial project. Experts of Loop Consulting Group have undertaken and provided the required support on the following issues at all stages of the construction management within the scope of the “Secondary Waste Water Treatment Plant and LPG Tank” project;
Determination and Assessment of the Risks, Scope Assessment, Bill of Quantities, Time and Cost Estimates, Preparing Baseline Work Schedules (Level-4), Human Resource and Machine-Equipment Resource Planning, Preparing Project Budget and Cash Flow, Preparing Mobilization and Demobilization Plans, Determination of Progress Measuring System, Preparing Progress Payments, Critical Path Method Analysis, Updating Work Schedule, Updating Budget and Cash Flow, Monitoring Work Schedule Performance, Monitoring Cost Performance, Earned Value Analysis, Work Schedule Delay Analysis, Window Analysis, Preparing Subcontractor Contracts, Change Management, Preparing, Discussing, and Resolution of Claims.
MS Project and Oracle Primavera Profesyonel P6” software programs were used actively and effectively in the planning and monitoring stages of the “Secondary Waste Water Treatment Plant and LPG Tank” project.
Client:

Inco International Fz. Co. LLC

Location:

Dubai, UNITED ARAB EMIRATES

Scope of the Work:

Time Management, Cost Management, Risk Management, Contract Management, Claims Management, and Change Management

Date:

2010