Trans Anatolian Natural Gas Pipeline (56″) Project, Various Regions, TURKEY

About This Project

With its total length of 1850 km, “Trans Anatolia Natural Gas Pipeline (56″)” Project passes through 20 cities in Turkey and ends at the border with Greece and has become first in many fields in the world with its technical features. It is a mega project with an investment value of billions of dollars. The Project aims to bring the resources derived from Shah Deniz-2, and other gas fields owned by Azerbaijan at the south of the Caspian Sea to Turkey and Europe. Experts of Loop Consulting Group have undertaken and provided the required support to the employer on the following issues at all stages of the construction management within the scope of the “Trans Anatolia Natural Gas Pipeline (56″)” project;
Assessment and Approval of Risk Prevention Plan, Assessment and Approval of Time and Cost Estimates, Assessment and Approval of the Baseline Work Schedules (Level-4), Linear Scheduling (Assessment and Approval of March Chart Diagram), Human Resource and Machine-Equipment Resource Planning, Preparing Project Budget and Cash Flow, Preparing Mobilization and Demobilization Plans, Assessment of Progress Measurement System, Assessment of Contractor Progress Payments, Critical Path Method Analysis, Assessment of Work Schedule Updates, Updating Project Budget and Cash Flow, Monitoring Work Schedule Performance, Monitoring Cost Performance, Earned Value Analysis, Time Impact Analysis, Cost Impact Analysis, Control and Approval of Change Demands, Examination and Interpretation of Claims, Preparing Counter Claims.
Oracle Primavera Project Profesyonel P6, Lineer Planlama yazılımı olan TILOS” and enVision as a Document Control software were used actively and effectively in the planning and monitoring stages of the “Trans Anatolia Natural Gas Pipeline (56″)” project.
Client:

SOCAR-BP-BOTAS

Location:

Various Regions, TURKEY

Scope of the Work:

Time Management, Cost Management, Risk Management, Contract Management, Claim Management, and Change Management

Date:

2017-2018